Scaffolding down, plastering up

All the scaffolding has been taken down and they have started plastering. I did request an independent inspection, but apparently our site supervisor forgot and went ahead to put up the plasterboards. I also did tell him that I wanted to add more downlights to the upstairs, but he misunderstood and thought I only wanted …
Continue reading Scaffolding down, plastering up

Timeline of events

Here is a summary of the dates since PD collapsed. 31/3/23 – Announcement 31/3/23 – Completed VMIA claim form 27/6/23 – VMIA accepted liability (I have no idea why it would take them 3 months to accept liability), maybe because of the volume of people affected? Apparently there were about 1500 homes left unfinished in …